Net present value (NPV) and internal rate of return (IRR)
Key Strokes |
Explanation |
Display Output |
[CF][2nd][CLR WORK] |
Clear CF memory registers |
CF0 = 0 |
400[+/-][ENTER] |
Initial cash outlay |
CF0=-400 |
[↓]100[ENTER] |
Period 1 cash flow |
C01=100 |
[↓][↓]200[ENTER] |
Period 2 cash flow |
C02=200 |
[↓][↓]300[ENTER] |
Period 3 cash flow |
C03=300 |
[NPV]8[ENTER] |
8 percent discount rate |
I/Y=8 |
[↓][CPT] |
Calculate NPV |
NPV=94.64 |
Example 1: Calculating the net present value |
|||||||||||||||||||||||||||
TVF Inc. is considering an investment in a project. The initial outlay of the project is $250,000. The expected cash inflows in the first two years are $30,000 and $40,000 respectively. The expected cash inflow from year 3 to year 8 is the same in each year and equal to $50,000. The project duration is eight years. Compute the NPV of the project and specify whether the project should be selected or rejected per NPV rule. The discount rate is 10 percent.
Since the net present value is a negative number, the company should reject the investment in the project. |
The internal rate of return (IRR) is another measure to check the profitability of a project. It is the discount rate that makes net present value equal to zero. It equates the present value of cash outflow to the present value of the cash inflows. It is called "internal" rate of return because it is dependent only on the cash flows of an investment and no external data are needed.
PV(Outflows) = PV(Inflows)
Calculating IRR using the financial calculator: Let's calculate the IRR of a project having an initial outlay of $300 and two cash inflows of $200 and $150 at the end of the first and second year respectively.
Key Strokes |
Explanation |
Display Output |
[CF][2nd][CLR WORK] |
Clear CF memory registers |
CF0 = 0 |
300[+/-][ENTER] |
Initial cash outlay |
CF0= -300 |
[↓]200[ENTER] |
Period 1 cash flow |
C01=200 |
[↓][↓]150[ENTER] |
Period 2 cash flow |
C02=150 |
[IRR][CPT] |
Calculate IRR |
IRR=11.51 |
IRR Rule: If the IRR is greater than the cost of the project, then accept the project. If IRR is less than the cost of the project, then reject the project.
Example 2: Calculating the internal rate of return |
||||||||||||||||||
Kotak Inc. is thinking of investing in a project that would generate cash flows of $200 each year for five years. The initial cash outlay for the project is $600. The cost of the project is 12.50 percent. Calculate the IRR of the project and interpret it.
The internal rate of return is 19.86 percent, and it is greater than the cost of the project (12.50 percent). Hence, the project should be selected. |